Six weeks to a forecast that outperforms yours See how

Planning notes

Notes on forecasting, ordering and inventory, written by the team.

Nov 9, 2026

Bottleneck analysis that survives a change in the mix

The capital request is for a second filler at 3.4 million, and the justification is one line: the filler runs at 92 percent. It has been in the plan for two years. On-time-in-full has not moved in either of them.

Nov 6, 2026

Distributed order management and the split shipment nobody priced

An order comes in with two lines. A pair of boots and a pair of socks. The boots ship from the east coast DC, the socks ship from a store in Ohio that happened to be four miles closer to the customer, and the customer receives two parcels on two days for a total order value of ninety. Nobody in the business made that decision. A rule engine made it twice, once per line, and each of the two decisions was locally correct against the objective it was given.

Nov 5, 2026

Ship from store when the alternative is a markdown in eight weeks

A customer in Leeds orders a lambswool jumper at 21:40 on a Tuesday. The distribution centre shows zero. Six of them are folded on a table in a store that has sold one in the last eight weeks, and that store will mark them down by forty per cent in early January because that is what happens to jumpers in early January. The order gets cancelled at 06:00 the next morning by a batch job, and nobody connects the two events.

Nov 3, 2026

Turnaround time sets the size of a repairable spare parts pool

The pool of hydraulic manifolds has sat at 180 units for four years and nobody has bought one since 2022. Every failure gets swapped in the field, the failed unit comes back, the shop strips and rebuilds it, and it returns to stock as serviceable. Last quarter availability on that manifold fell to 71 percent and the request that came up the chain was to buy thirty more at four thousand pounds each. At the same moment the shop had ninety of them stacked against a wall waiting for a seal kit worth eleven pounds.

Nov 2, 2026

The release notes said no functional change and the plan moved

The vendor ships release 24.3 over a weekend. The notes list performance improvements, a security fix, and two defect corrections in modules you do not use. Nothing under functional change.

Oct 30, 2026

Your planning support queue is three different jobs in one inbox

At 05:40 the demand feed lands with zero rows, because an upstream export ran while the source table was locked. The chain treats an empty file as a valid file. Every downstream step succeeds, the run completes eleven minutes early, and at 07:00 the system publishes a supply plan built on demand history that stops a week ago.

Oct 29, 2026

Vietnam supply chain planning when the inputs still come over the border

The plan says the plant in Bac Ninh runs at eighty five per cent of nameplate through the quarter. It has not done that in eighteen months, and the shortfalls do not line up with anything in the demand file. Two of them start on a Tuesday in June. One runs for nine days after the lunar new year and then recovers to about ninety per cent of the pre-holiday rate and stays there for a month. Another follows a week when trucks stopped arriving from Lang Son. None of these is an efficiency problem, and none of them is visible in a capacity model that carries a single availability percentage.

Oct 28, 2026

Covering an emissions obligation before the deadline decides the price for you

The surrender deadline is in April. The buying happens in February and March, because that is when the treasury team gets the verified emissions figure, works out the shortfall against the allowances already held, and goes to the market with a number.

Oct 27, 2026

Mexico nearshoring supply chain planning when the crossing is the longest lead time

The plan that justified the plant has one number in it that turns out to be wrong. Transit from the new site in Guanajuato to the customer's distribution centre outside Chicago went in at four days, which is what the carrier quoted. Six months into production the measured door to door is running between five and eleven days, the spread comes almost entirely from a few hundred metres of bridge at Laredo, and the safety stock sized for a four day lead time with no variance is why the customer has started asking questions about the ramp.

Oct 26, 2026

Feedstock price pass-through when the formula moves the volume

The March contract price settles up eighty euro a tonne. The commercial team is comfortable, because every major customer sits on a formula that passes the increase straight through, so margin per tonne is protected by construction. February then closes at 14,400 tonnes against a plan of 12,000, and the plant runs seven days with overtime to cover it. April closes at 9,900. The demand review in early March reads February as a strong month and raises the rest of the quarter. The demand review in early May reads April as a demand problem and cuts it back.

Oct 23, 2026

Hazardous materials transportation planning when one kilo changes the rules

A distribution centre has shipped the same solvent to the same customer every week for three years. Twelve cases, 300 litres, on a standard van, one transport document, no orange plates, no specially certified driver. The planner running a consolidation exercise notices the lane and moves it to fortnightly at 600 litres, which halves the shipment count and looks like a straightforward win on the freight line.

Oct 22, 2026

A ninety-day product with seventeen usable days

The specification sheet says ninety days. The retailer's supply agreement says seventy five per cent of life remaining on delivery, which is sixty seven and a half days, so the stock has to arrive within twenty two days of the production date. Quality release takes three days because the micro results come back on day two and the paperwork moves on day three. Transit to the regional distribution centre is two days. Picking and outbound is another day at the volumes involved.

Oct 21, 2026

Capture cost is mostly decided before you pick a technology

Take one industrial site with two capture opportunities on it. The first is the process vent from a chemical unit, where the gas leaving the reactor is almost pure CO2 because the process separates it as part of making the product. The second is the exhaust from the gas turbines that power the site, where CO2 sits at a few percent in a stream that is mostly nitrogen.

Oct 20, 2026

The allergen matrix decides the sequence before the due dates do

It is Thursday and a customer has pulled forward an order for a mustard dressing on the sauces line. The scheduler agrees, because the customer is large and the line has the hours. What the schedule does not show is that the pull inserts the mustard run between two free-from products, so the week now contains three validated cleans instead of one. Each is five hours and twenty minutes of wet clean plus a hold for the swab result. The line loses most of a shift, the Friday orders slip, and the weekly review records it as a capacity problem.

Oct 19, 2026

Cell and gene therapy supply chain planning when the batch is one patient

The apheresis slot was booked for Tuesday. The manufacturing slot was booked seventeen days out on the strength of it. On Monday the patient's lymphocyte count came back too low to collect, the physician deferred by a week, and now there is a suite reserved for cells that do not exist.

Oct 16, 2026

Patent cliff planning when the forecast has never seen a cliff

The demand plan for the product that loses exclusivity in fourteen months still shows a gentle upward trend. The statistical model built it from four years of history, every month of it under patent, and it has extrapolated the only pattern anyone ever showed it. Meanwhile the site has a campaign booked in nine weeks that will produce something close to eleven months of cover at the current run rate, and the active ingredient for the campaign after that has to be ordered in March.

Oct 15, 2026

Store clustering when the groups were drawn by region and size

Four hundred stores sit in twelve clusters. The clusters were built from a grid: three trading regions crossed with four size bands. Every category uses them, because they came down from a project five years ago and nobody has had a reason to rebuild them.

Oct 14, 2026

Nobody builds the hydrogen plant until somebody signs for the molecule

The investment paper is thorough. Levelised cost per kilogram, a sensitivity grid across power price and utilisation, an engineering estimate with contingency, a permitting schedule, a grid connection queue position. The technical work has been done properly and the numbers are defensible.

Oct 13, 2026

On shelf availability and the four units that do not exist

A colleague walks the aisle with a handheld, finds a gap where a 500ml shampoo should be, and scans the shelf label. The screen says four on hand. There is no order to raise, because the system believes the store has stock and the replenishment run agrees. The gap is still there the following week, and the week after. Nine weeks later somebody does a count for an unrelated reason, corrects the record to zero, and the item ships on the next delivery.

Oct 12, 2026

What supply chain planning outsourcing can take off your desk

The statement of work said the provider would produce the statistical baseline, maintain planning parameters and clear the exception queue. Three roles came off the internal headcount. Twelve months later the internal team spends Monday and half of Tuesday reviewing what the provider produced, which is more time than the three roles used to spend producing it.

Oct 9, 2026

Warranty claims forecasting when the recent months are still filling in

The quality review in November has a chart on it that everybody likes. Claims per thousand units for machines shipped in the third quarter are running about 40 percent below the cohort before them, and the supplier change made in June is getting the credit. By the following March that cohort has caught its predecessor and gone slightly past it. The June change has been rolled out across two more lines on the strength of a number that was never real, and nobody reopens the November slide.